Exciting Changes Incoming at Beenleigh Aquatic Centre
Logan City Council is pleased to advise that Stage 2 of the Beenleigh Aquatic Centre upgrade commenced in March 2024. The project will replace the 60-year-old outdoor pool and buildings to support an active and healthy community.
The Project is identified in Council’s Community Infrastructure Strategy and will complete the upgrades identified in the Dauth Park Masterplan endorsed by Council in 2018.
In July and August of 2022, we asked the community to tell us their needs and vision for a new outdoor pool in Beenleigh. Feedback from close to 400 community members has been incorporated into the design which will include the following:
- 50m heated pool
- Expanded children’s play area
- Shaded seating areas
- Multipurpose rooms
- Modern changeroom facilities
- Kiosk
- Accessible features including ramps and hoists
- New carpark
The new outdoor pool is expected to be opened late 2025.
A fly through of the new facility is available below.
The existing pool is over 60 years old and nearing the end of its useful life. The upgrade will complete Stage 2 of the Dauth Park Masterplan which was endorsed by Council in 2018.
The existing pool is over 60 years old and nearing the end of its useful life. The upgrade will complete Stage 2 of the Dauth Park Masterplan which was endorsed by Council in 2018.
Based on community feedback from close to 400 respondents, the upgrades will include construction of a new outdoor 50m heated pool, expanded children’s play area, shaded seating areas, multipurpose rooms, modern changeroom facilities, kiosk, accessible features including ramps and hoists and a new carpark. The upgrade also includes a community stage facing Centenary Park for community concerts and events.
Based on community feedback from close to 400 respondents, the upgrades will include construction of a new outdoor 50m heated pool, expanded children’s play area, shaded seating areas, multipurpose rooms, modern changeroom facilities, kiosk, accessible features including ramps and hoists and a new carpark. The upgrade also includes a community stage facing Centenary Park for community concerts and events.
The indoor pool will remain open for all existing programs including aqua aerobics and swimming lessons. Council will do its best to manage any impacts on users. Please be aware access to the grassed areas of Centenary Park will be limited during construction and there will be additional noise and minor disruptions which will be proactively managed during construction.
The indoor pool will remain open for all existing programs including aqua aerobics and swimming lessons. Council will do its best to manage any impacts on users. Please be aware access to the grassed areas of Centenary Park will be limited during construction and there will be additional noise and minor disruptions which will be proactively managed during construction.
- March 2024: Construction on the new carpark scheduled to start.
- April 2024: Outdoor pool will be closed from the 15th of April and demolition of the existing outdoor pool and buildings is scheduled to start.
- May 2024: Construction of the new outdoor pool is scheduled to start.
- March 2024: Construction on the new carpark scheduled to start.
- April 2024: Outdoor pool will be closed from the 15th of April and demolition of the existing outdoor pool and buildings is scheduled to start.
- May 2024: Construction of the new outdoor pool is scheduled to start.
The new Beenleigh Aquatic Centre carpark will open on Thursday 15th August 2024. Entry and exit via Alamein Street only.
The new Beenleigh Aquatic Centre carpark will open on Thursday 15th August 2024. Entry and exit via Alamein Street only.
Council has pools across the city that residents can access. For more information on community pools and their operating hours visit the this link.
Council has pools across the city that residents can access. For more information on community pools and their operating hours visit the this link.
Members can use the Logan North Aquatic Centre during redevelopment. Access is included in Platinum and Blue memberships. Aqua aerobics will continue to run in the Beenleigh Aquatic Centre indoor pool during construction.
Members can use the Logan North Aquatic Centre during redevelopment. Access is included in Platinum and Blue memberships. Aqua aerobics will continue to run in the Beenleigh Aquatic Centre indoor pool during construction.
Yes, there will be no changes to swimming lessons.
Yes, there will be no changes to swimming lessons.
The Beenleigh Brass Band will be using the Crete Street Theatre during construction and will have access to a storeroom, multipurpose room and stage as part of the new aquatic centre development.
The Beenleigh Brass Band will be using the Crete Street Theatre during construction and will have access to a storeroom, multipurpose room and stage as part of the new aquatic centre development.